LA bridge closes for deck repair
The Vincent Thomas Bridge shuts down for 16 months to fix its deteriorating surface before the 2028 Olympics.
By Evelyn Ellis ·

The Vincent Thomas Bridge will stop carrying cars and trucks at 12:01 a.m. on Saturday. This closure marks the start of a 16-month construction period. The project aims to repair the aging structure that links San Pedro with Terminal Island and the Port of Los Angeles.
Caltrans has allocated $750 million for the work. The bridge, which is over 60 years old, handles approximately 53,000 vehicles every day. Heavy trucks make up nearly 9% of that total volume. Officials state the main structure remains sound, but the deck has worn down due to salt air and constant heavy traffic.
Construction crews will swap out the deck, median, railings, fencing, and signs. They will also upgrade the seismic sensors on the bridge. The goal is to reopen the span in March 2028. This date falls roughly four months before the Los Angeles Olympics begin.
The timing is intentional. The Port of Los Angeles will host six sailing events during the games. These include men’s and women’s dinghy races, skiff competitions, and mixed multihull events. Belmont Shore will handle the board sports, windsurfing, and kiteboarding competitions.
Drivers must find alternate routes during the closure. The primary detours will use the 110 and 710 freeways, state Route 103, and Harry Bridges Boulevard. Traffic control officers will manage flow at 18 specific intersections. Police will also increase enforcement of rules restricting commercial trucks on local roads.